  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.C94086
 Project Type:Interceptor
 Project Category:Interceptor
 MSD Project Manager:Steve Emly
 Jurisdiction:LOUISVILLE
 Metro Council District:22ROBIN ENGEL

 KY Senate District:

38DAN "MALANO" SEUM
 KY House District:29KEVIN BRATCHER
Project Schedule
  Project Start:3rd Quarter 2006
  Planning Complete:3rd Quarter 2007
  Easements Complete:4th Quarter 2007
  Bidding Complete:1st Quarter 2008
  Construction Complete:3rd Quarter 2008
No. Properties:5

Estimated Capital Cost:

      (2008 dollars)

$650,000.00
Service Area:West County WTP
Project Dependent On:Fern Creek/Nottingham Int. #6
Project Status:Under Construction
Area Team:POND CREEK/MILL CREEK
Watershed:POND CREEK
LOJIC Street Atlas:MAN22,MAN22
MSD Atlas:BM234
             Budget ID #  C94086

 

Fern Hill Subdivision Interceptor #8

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

This project includes 1,200 LF of 10-inch gravity sewer and will eliminate the Holly Oaks P.S.

 

 

Need

 

Elimination of Holly Oaks P.S. is required by Consent Decree.

 

 

Other Information

Downstream half of this interceptor project was added to the Fern Creek/Nottingham Interceptor #6 project to eliminate the Fern Hill Wastewater Treatment Plant located at Story Brook Drive and Hurstbourne Parkway. The upstream portions may be designed and constructed by private development.