Louisville-Jefferson County

Metropolitan Sewer District

Wolf Pen Branch Interceptor Sanitary
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.D94213
 Project Type:Interceptor
 Project Category:Interceptor
 MSD Project Manager:Vicki Coombs
 Jurisdiction:LOUISVILLE, PROSPECT
 Metro Council District:16KELLY DOWNARD

 KY Senate District:

26ERNIE HARRIS
 KY House District:48BOB M. DEWEESE
Project Schedule
  Project Start:Not Applicable
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:Not Applicable
  Construction Complete:Not Applicable
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$2,350,000.00
Service Area:Morris Forman WTP
Project Dependent On:Harrods Creek Interceptor
Project Status:Outside 5 Year Plan
Area Team:FLOYDS FORK/NORTH COUNTY/MFWTP
Watershed:HARRODS CREEK
LOJIC Street Atlas:MAJ23,MAJ22
MSD Atlas:AK236,AI234
             Budget ID #  D94213

 

Wolf Pen Branch Interceptor Sanitary

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

This project consists of interceptor sewer segments along Wolf Pen Branch Creek upstream from the Harrods Creek Interceptor sewer. The project requires approximately 6,050 LF of 18-inch and 1,700 LF of 24-inch gravity interceptor sewer.

 

 

Need

 

This project will extend sewers to areas which are not fully developed or where existing residential subdivisions are using on-site disposal systems.

 

 

Other Information

None.