Louisville-Jefferson County

Metropolitan Sewer District

Monticello Pump Station Expansion
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.E00304
 Project Type:Pump Station
 Project Category:Pump Station
 MSD Project Manager:Vicki Coombs
 Jurisdiction:JEFFERSONTOWN
 Metro Council District:20STUART BENSON

 KY Senate District:

19TIM SHAUGHNESSY
 KY House District:31STEVE RIGGS
Project Schedule
  Project Start:Not Applicable
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:Not Applicable
  Construction Complete:Not Applicable
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$137,000.00
Service Area:Jeffersontown WTP
Project Dependent On:Not Applicable
Project Status:Outside 5 Year Plan
Area Team:FLOYDS FORK/NORTH COUNTY/MFWTP
Watershed:POND CREEK
LOJIC Street Atlas:MAM23
MSD Atlas:BK236
             Budget ID #  E00304

 

Monticello Pump Station Expansion

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

This project will evaluate the existing Monticello Pump Station and expand the pump station to handle all potential sanitary sewer flows within its existing service area.

 

 

Need

 

The existing pump station is near capacity due to development and Inflow and Infiltration issues. This project will be initiated as needed.

 

 

Other Information

None.