WCWTP Liquid Process Phase 4
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.F01396
 Project Type:Treatment Plant
 Project Category:WCWTP
 MSD Project Manager:Sharon Worley
 Jurisdiction:LOUISVILLE
 Metro Council District:14ROBERT HENDERSON

 KY Senate District:

10ELIZABETH TORI
 KY House District:44JONI L. JENKINS
Project Schedule
  Project Start:Not Applicable
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:Not Applicable
  Construction Complete:Not Applicable
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$6,410,000.00
Service Area:West County WTP
Project Dependent On:Not Applicable
Project Status:Outside 5 Year Plan
Area Team:FLOYDS FORK/NORTH COUNTY/MFWTP
Watershed:MILL CREEK
LOJIC Street Atlas:MAO15,MAO15
MSD Atlas:CA206,CA204
             Budget ID #  F01396

 

WCWTP Liquid Process Phase 4

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

Increase the capacity and reliability of the WCWTP Raw Sewage Pump Station by replacing 2 existing 13.5 mgd pumps with larger pumps and replacing obsolete pump drives with new variable frequency drives.

 

 

Need

 

Projected increases in wet weather flows require added pumping capacity.

 

 

Other Information