WCWTP Liquid Process Phase 4
| |||
| |||
Project Description
Increase the capacity and reliability of the WCWTP Raw Sewage Pump Station by replacing 2 existing 13.5 mgd pumps with larger pumps and replacing obsolete pump drives with new variable frequency drives. | |||
Need
Projected increases in wet weather flows require added pumping capacity. | |||